Cartmell Place Construction Update

September 2017 Update:

Works on site continue to progress well.

The building has been entirely clad, windows installed (save for the entry glazing) and handrails and balustrades are largely in place.

Fixed plantar boxes have been constructed and external paving to balconies & courtyards have commenced. Canopies have been erected and painting work is progressing well.

Internally, apartments have been plastered and painted. Tiling to the wet areas has been complete and kitchen & bathroom joinery units have been installed. Floor finishes (excluding carpets) are largely complete and the installation of plumbing fixtures and fittings is well progressed whilst the electrical and mechanical fit-off continues.

Lifts have been installed and work to the lift lobbies have commenced. Common area hallways have been plastered & painted and individual service meters are largely installed.

The emphasis for the remainder of September is to conclude services within the basement layers and finalise the authority/utility connections to the building.

The project remains on track for completion in late 2017.